Category:East Side Access construction/2020/01/10
Jump to navigation
Jump to search
Media in category "East Side Access construction/2020/01/10"
The following 26 files are in this category, out of 26 total.
-
Excavating for the fire line for the future Mid-Day Storage Yard. (49363751751).jpg 3,516 × 1,978; 1.93 MB
-
Installing a tile wall mockup in the future LIRR Terminal. (49363293138).jpg 4,032 × 3,024; 4.14 MB
-
Installing rebar for the duct banks at the future Mid-Day Storage Yard. (49363292788).jpg 3,516 × 1,978; 2.48 MB
-
Placing concrete for the duct bank in the future Mid-Day Storage Yard. (49363966477).jpg 3,516 × 1,978; 1.92 MB
-
Pouring concrete between piles for the future Mid-Day Storage Yard. (49363751676).jpg 1,512 × 2,016; 1.11 MB
-
Removing an equipment pad for replacement in a substation In Queens. (49363292933).jpg 3,456 × 4,608; 6.14 MB
-
Termination of the pulled fiber optic cables for a system in Queens. (49363751896).jpg 4,608 × 3,456; 2.57 MB